Not everybody has home by nature
At the Stage of Implementation

Now, the company is implementing following projects

Project NameShort Information Concerning Project
Construction of shopping centre in the area of house 11 in Kirova Street in Dnepropetrovsk Customer: "Karat" Ltd
Prime contractor: SJC BC "Prioritet"
Total floorspace is 11230,0 m2.

Construction activities to raise apartment block in 21, Voroshiliva Street in Dnepropetrovsk Customer: ООО "Zhovtnevy-14"
Contractor: SJC BC "Prioritet"
- Installation of precast reinforced concrete cage from 5-th to 15-th storey
- Brick-laying from basement to 15-th storey
- Building of parking
Construction of 25-storey apartment block with administrative premises in a housing area "Sokol" near building 56 in Slava Boulevard in Dnepropetrovsk Own construction
Construction volume is 58432,0 m3.
Total floorspace of the building is 14300,0 m2.
Total floorspace of flats is 12000,0 m2.
Construction of apartment block in a housing area "Sokol" near building 56 in Slava Boulevard in Dnepropetrovsk Own construction
Total floorspace of flats is 3 100,0 m 2
Construction of two-sectional apartment block in a housing area "Klochko-6" in Kholodilnaya Street in Dnepropetrovsk Own construction
Two-sectional block of flats (15, 17 storeys)
Total floorspace of flats is 8 300, 0 m 2.
Construction and designing of commercial building in Avenue Gazety "Pravda" in Dnepropetrovsk Own construction
Commercial building with trade premises at the corner of Avenue named after newpaper "Pravda" and Batumskaya Street
Construction volume is 7326,5 m 3
Total floorspace of the building is 1598,6 m 2.
Trade floorspace – 1132,6 m 2
Construction of trade and office centre in Poltava Prime contractor: BC "Ukrrosmetall"
Subcontractor: SJC BC "Prioritet"
Activities to make monolith reinforced concrete frame (columns, ceilings)
Construction volume is 14000, 0 m 3.